Historical Highlights
Historical Highlights
2021
Two New Fuel Efficient Engines Installed at Cane Hall Power Station
2020
Testing and commissioning of the Mayreau Microgrid Solar Farm
2019
Official opening of the Union Island Solar Photovoltaic and battery energy storage facility
2018
Official re-opening of the Richmond and South Rivers Hydro Stations after rehabilitation
2017
Installation of two new generators at the Union Island Power Station
2016
Commencement of works to rehabilitate the South Rivers hydroelectric plant
Installation of diesel unit no. 2A in Mayreau (80 kW). This followed decommissioning of original 60 kW Unit no. 2.
2015
Rehabilitation of Richmond Hydro Station and pipeline were completed
The 11 kV switchgear and housing facility at South Rivers was commissioned
2014
Commissioning of the Lowmans Bay 370 kWdc Solar PV system
Installation of first set of LED streetlights
Installation of diesel unit # 4 in Mayreau (104 kW)
Completion of Annex to Corporate Headquarters in Kingstown
2013
Contract signed between VINLEC and Gilkes for the refurbishment of the South Rivers and Richmond Hydro Power Stations
Major rehabilitation of Union Island Power Plant completed
A 177kW grid tied photovoltaic system at the Cane Hall Engineering Complex officially commissioned
Major damage to hydroelectricity system in December from flooding
2012
The company began the implementation of a major Fire Safety Protection Project
Expansion of the 11 kV distribution with the addition of the Belair Feeder (2.7 kM)
Electronic Bill Notification launched
2011
The company celebrated its 50th Anniversary in November
Official opening of the Lowmans Bay Power Plant as part of activities to commemorate the 50th anniversary
Expansion of 33 kV transmission system (including the building and commissioning of the South Rivers Substation)
Commencement of a second phase of wind data collection at Diamond
2007
VINLEC officially took ownership of the Lowmans Bay Power Plant. The generating capacity was 8.7 megawatts (MW). At that time the Plant provided just over 30 percent of power on mainland, St. Vincent
2005
Ground breaking for Lowmans Bay on the South Western coast of St. Vincent.
1995
Corporate Headquarters in Paul’s Avenue was officially opened
1994
A 1080kW Power Plant was commissioned in Canouan. At the time, the Plant was producing power to 220 customers.
1993
Villages North of the Rabacca Dry River were electrified as part of the North Windward electrification programme
1988
Two additional engines were installed at Cumberland Station
1987
Third Hydro station at Cumberland was commissioned with three engines
1985
The St. Vincent Electricity Services Limited became a state owned enterprise
1976
Cane Hall Power Station was officially commissioned
1974
Union Island power station was commissioned and the Fuel Surcharge was introduced
1973
Electricity Supply Act gave VINLEC exclusive license to supply electricity
1971
Government of SVG acquired 49% of the shares of VINLEC
1968
Bequia Power Station was commissioned
1967
VINLEC signed an agreement with the government of St. Vincent and the Grenadines to supply electricity to Bequia
1962
2nd Hydro Station: Richmond Power Station
1961
St. Vincent Electricity Services Limited was incorporated
1953
Multi-National Corporation-Commonwealth Development Corporation (CDC) took ownership of the Electricity Company
1952
The first Hydro Station opened at South Rivers Power Station.
1937
All day electricity service was introduced to 478 customers
1931
Public electricity services were initiated in the Colony of St. Vincent